Build-out and occupancy permits in San Jose

Plan review, building and occupancy approvals for the space.

Updated October 15, 20264 filingsSources: the agencies' own sites

  1. Food facility plan check

    County of Santa Clara Department of Environmental HealthSCC

    Email the application, scaled plans, menu and equipment sheets to dehplancheck@deh.sccgov.org, then pay the invoiced review fee. The city needs the county's stamped plans before its own plan check.

    Fee
    Varies
    Filed
    Paper form, mailed
    Takes
    After payment, inspector review may take up to 20 business days.

    File on the agency's siteHow to fill it

  2. Building permit for a tenant improvement

    City of San José Building DivisionSan Jose

    Apply on SJPermits.org, upload plans through SJePlans and pay the plan review fee before review starts. Restaurants can use the city's Streamlined Restaurant Program.

    Fee
    Varies
    Filed
    Filed on the agency's portal
    Takes
    San José's standard plan review for a commercial tenant improvement takes about 10 working days for the first round and 5 working days for each recheck.

    File on the agency's siteHow to fill it

  3. Fire protection system permit

    San José Fire Department, Bureau of Fire PreventionSan Jose

    When plan check calls for it, apply on SJPermits.org under Fire Prevention, pay, then upload documents in SJePlans.

    Fee
    Varies
    Filed
    Filed on the agency's portal
    Takes
    Fire Department review of fire protection system plans takes about 10 working days for the first round and 5 working days for each recheck on a commercial project.

    File on the agency's siteHow to fill it

  4. Building final inspection

    City of San José Building DivisionSan Jose

    Schedule the final on SJPermits.org once every other inspection on the permit has passed.

    Fee
    Varies
    Filed
    Filed on the agency's portal
    Takes
    San José doesn't publish a wait time for the final inspection; you request it on SJPermits.org, and it's approved only after every other inspection on the permit has passed.

    File on the agency's siteHow to fill it

Guides for each business in San Jose

Agency requirements change. Check each agency's page before you file.

Get the plan for your business in San Jose

This guide covers the city. Your exact address decides the county, the health district and the zoning. Placetta maps every filing for it, fills the official forms from your details, adds the deadlines and puts them up for your approval.

  • The full list for your address, in filing order
  • The official forms, filled line by line
  • Renewal and inspection reminders

Free to start, no card needed. We only use your email to reach you.

Get my plan for San Jose