Build-out and occupancy permits in Austin

Plan review, building and occupancy approvals for the space.

Updated October 15, 20263 filingsSources: the agencies' own sites

  1. Certificate of Occupancy

    City of Austin Development ServicesAustin

    Needed when the space's use changes or after construction; it may include a site plan exemption and building plan review. For a food business it comes through Austin Public Health's pre-opening inspection.

    Fee
    Varies
    Filed
    Filed on the agency's portal
    Takes
    Change-of-use reviews now take about two weeks (three review disciplines since October 2025).

    File on the agency's siteHow to fill it

  2. Building permit for a tenant finish-out

    City of Austin Development ServicesAustin

    Apply with the city's commercial building permit web form (not AB+C) to build, alter or convert the space, with plans for commercial plan review.

    Fee
    Varies
    Filed
    Filed online
    Takes
    Commercial plan review for a remodel up to 25,000 sq ft takes 10 business days; small projects, such as a finish-out under 10,000 sq ft, take 5 business days.

    File on the agency's siteHow to fill it

  3. Food establishment plan review

    City of Austin Development Services, with Austin Public HealthAustin

    For new construction or a remodel: inside the City of Austin, apply online through Development Services; in unincorporated Travis County, through Austin Public Health's My Health Department portal.

    Fee
    $312
    Filed
    Filed online
    Takes
    Inside the City of Austin, the food plan review is submitted with the commercial building application, whose review takes 10 business days for a remodel up to 25,000 sq ft (5 for small projects).

    File on the agency's siteHow to fill it

Guides for each business in Austin

Agency requirements change. Check each agency's page before you file.

Get the plan for your business in Austin

This guide covers the city. Your exact address decides the county, the health district and the zoning. Placetta maps every filing for it, fills the official forms from your details, adds the deadlines and puts them up for your approval.

  • The full list for your address, in filing order
  • The official forms, filled line by line
  • Renewal and inspection reminders

Free to start, no card needed. We only use your email to reach you.

Get my plan for Austin